The A12 has 7 closures listed across Essex for the week beginning 23 November 2026, more than any other road in the published figures. The M11 has 5, the A13 has 3 and the M25 has 2.
The notices cover different kinds of work, from lane restrictions to carriageway and slip-road closures. They do not all mean the whole road will be shut.
Which Essex roadworks could add the longest delays?
The works below are the ones where National Highways expects moderate delays of 10 - 30 mins. Dates show when each notice starts and ends; the notices do not give daily opening or closing times.
| Road | Direction and section | Starts | Ends | Expected delay | Diversion listed |
|---|---|---|---|---|---|
| A12 | Southbound, Jct 28 to Jct 26 | 28 November 2026 | 30 November 2026 | 10 - 30 mins | Diversion route listed, but route not specified |
| A12 | Both directions, Jct 27 to Jct 29 | 23 November 2026 | 28 November 2026 | 10 - 30 mins | Not specified |
| M11 | Southbound, Thremwell Avenue to Jct 8 | 23 November 2026 | 28 November 2026 | 10 - 30 mins | Not specified |
| A13 | Eastbound, Lakeside Interchange to Wennington Lane and slip road | 26 November 2026 | 27 November 2026 | 10 - 30 mins | Local Authorities and National Highways Network |
| M25 | Clockwise, Jct 25 to Jct 27 | 23 November 2026 | 28 November 2026 | 10 - 30 mins | Local Authorities and National Highways Network |
| M25 | Clockwise, Dartford Crossing QEII Bridge Jct 31 to A282 Southbound Jct 2 | 23 November 2026 | 28 November 2026 | 10 - 30 mins | National Highways and Local Authorities Network |
| M25 | Clockwise, Jct 29 to Jct 30 | 23 November 2026 | 28 November 2026 | 10 - 30 mins | Local Authorities and National Highways Network |
| A406 | Westbound, Redbridge roundabout to M11 Northbound Jct 4 link road | 23 November 2026 | 27 November 2026 | 10 - 30 mins | Local Authorities and National Highways Network |
Source: National Highways planned roadworks notices, covering works starting from 23 November 2026.
What other A12 closures and lane restrictions are listed?
The A12 notices include a southbound carriageway closure between Jct 28 and Jct 26, as well as works between Jct 27 and Jct 29 in both directions. Both are expected to cause moderate delays.
Other notices include a northbound entry-slip closure at Jct 22, a southbound entry-slip closure between Jct 21 and Jct 20, and works around Hatfield Peverel and Witham. Those are each listed with expected delays of less than 10 mins.
The A12 count is a count of listed closures, not a count of full-route shutdowns. Notices also cover lane and slip-road restrictions, and some refer to more than one road.
Where can drivers check roadworks before travelling?
Check National Highways live travel updates for current notices and diversion details. Essex Highways also provides local road and traffic information.
The notices give start and end dates but not the hours when restrictions will be in force. Check again before setting off, particularly if your journey uses the A12, M25 or Dartford Crossing.
About the figures
National Highways published the planned roadworks notices between 22 January 2026 and 13 November 2026. The closure counts refer to the week beginning 23 November 2026, while some individual works continue until 4 December 2026.
Expected delays are estimates, not reports of actual journey times. The notices do not state daily work hours, and the listed restrictions range from lane closures to carriageway and slip-road closures.