Update 12:22pm on Monday 23 November 2026
National Highways no longer lists these roadworks.
Drivers using the M25 clockwise QEII Bridge at West Thurrock should allow for expected delays of 10 - 30 mins during an overnight closure for bridge maintenance.
The crossing is scheduled to close at 10:30pm on Saturday 21 November 2026 and reopen at 5:30am on Sunday 22 November. The Junction 31 entry slip road is due to close from 10:30pm too.
Which M25 junctions will be affected near West Thurrock?
The bridge closure runs from Junction 31 to Junction 1A on the clockwise M25, covering the Dartford Crossing. The separate closure of the M25 clockwise Junction 31 entry slip road will affect drivers trying to join the motorway near West Thurrock.
The roadworks notice gives the bridge closure’s planned end as 5:30am on Sunday 22 November. It does not give a separate reopening time for the entry slip road.
What diversion should drivers follow at the Dartford Crossing?
For the bridge closure, the stated diversion is via the National Highways network. For the Junction 31 entry slip road, the diversion is via local authorities and the National Highways network. Follow the temporary signs on approach.
What should drivers check before setting off?
Check National Highways live travel updates before leaving, as planned closures can change. Drivers can also check Essex Highways for local road information.
About the figures
National Highways’ planned roadworks notice, published on 19 February 2026, lists bridge maintenance from 10:30pm on Saturday 21 November 2026 to 5:30am on Sunday 22 November 2026, with expected delays classed as moderate (10 - 30 mins). The separate Junction 31 entry slip road closure is listed as starting at 10:30pm on Saturday 21 November, but no reopening time is given for it.
These are planned times, not a guarantee that the closure will start or end exactly as scheduled. Check National Highways’ live travel updates before setting off.